Fairfax County Program Design and Development Status Report - August 2005
| Project |
Description |
Completion Date |
Status |
| Clifton
Road |
Design and construction of
a 4-lane roadway from Lee Highway to Braddock Road for a total of
approximately 2,500 LF. |
December-05 |
Construction is 77%
complete. |
| Fairfax
County Parkway Widening |
Widening of Fairfax County
Parkway to six lanes from Rugby Road to Dulles Toll Road for a total of 6.5
miles. Additional lane to be HOV lane. |
TBD |
Preliminary survey data
received for northern section. Funding for preliminary engineering and
environmental studies only. Traffic analysis to be extended south to include
section between I-66 and Rugby Road. Coordination meeting with FHWA held on
9/8/05. |
| Lee
Highway (Route 29) |
Widening segments along Lee
Highway from Shirley Gate Road to Old Centreville Road from 4 to 6 lanes. |
TBD |
Estimated TPE is for design
only. Schedule will be determined following completion of preliminary design
review. Preliminary design submitted 7/28/05. Scoping meeting being held this
month. Awaiting comments. |
| Old
Centreville Road Trail |
Asphalt trail from Old
Mill Community to Park and Ride at
Centreville Methodist Church for a distance of approximately 800 LF. |
December-06 |
Project is part of the
Four-Year Transportation Plan and was approved by the BOS 3/21/05. Project
design to be completed by a developer and construction by DPWES. Intermediate
design was submitted for review 8/1/05. VDOT comments received 9/6/05. |
| Poplar
Tree Road |
Additional left turn-lane
on westbound Poplar Tree Road at the intersection with Stringfellow Road. |
May-06 |
Project is part of the
Governor's Congestion Relief Program, funded by VDOT. Pre-final design
submitted to VDOT for review on 8/17/05. Authorization to proceed with signal
design given to Consultant on 8/15/05. |
| Route
29/66 Underpass Trail |
1800 LF 8' asphalt trail,
including crossing under I-66 overpass. |
July-06 |
Project is part of the
Four-Year Transportation Program endorsed by the BOS on 2/9/04. Pre-final
design plans were distributed on 9/1/05. |
| Route
29/Bull Run Post Office Road |
Install right turn-lane on
southbound and left-turn on northbound Route 29, improve alignment and
provide turn lanes for Bull Run Post Office Road |
January-06 |
Construction
substantially complete. Awaiting VDOT inspection. Traffic signal work by VDOT
is complete. |
| Route
50 Interchange/ Waples Mill Road |
Design and construction of
at-grade improvements. |
August-06 |
Project is part of the
Four-Year Transportation Program endorsed by the BOS on 2/9/04. Utility
relocations are complete. Notice-to-proceed issued 8/1/05. Roadway open cut
and noise variance requests have been requested. Acquisition authorization
given 8/9/05. |
| Stone
Road |
Construct
a raised median from Rte. 29 Lee Highway to Billingsgate Lane, widen roadway
from Billingsgate/Battery Ridge Lane to Awbrey Patent Drive, and install a
traffic signal at Stone Road and Billingsgate/Stone Path intersection. |
August-07 |
Public meeting scheduled
for 10/5/05, to present plans. Land Acquisition authorization given 8/9/05. |
| Stonecroft
Boulevard Widening |
Widen Stonecroft Boulevard
to a six-lane section from Conference Center Drive to Westfields Boulevard. |
TBD |
Fairfax County responsible
for 800' of improvements in front of Sully District Government Center with
the remaining portions to be completed by developers. Schedule contingent
upon completion of design or developer's portion of project. Site plan
submitted to OSDS on 8/29/05. |
| West
Ox Road/Monroe Street |
Eastbound left turn-lane
from West Ox Road to Monroe Street. |
August-07 |
Pre-final plans submitted
for review 7/20/05. Pre-final plan comments received on 9/6/05. A UFI was
held on 9/5/05. Land Acquisition plat submission was 8/26/05. |